Construction of basement with Larsen piles combined with Shoring kingpost system

The name of construction : SCHOOL HOUSE – HCMC UNIVERSITY OF FINE ARTS.
Address: No. 5 Phan Dang Luu - Binh Thanh District - Ho Chi Minh City
Category :
– Rental, installation and dismantling of larssen steel piles and rental of shoring systems.
– Construction of soil excavation, backfilling and soil transportation
Construction unit : Le Thy Construction Company Limited

Project images

Basement construction

Housing needs are always changing to meet the increasing living needs of people. Among them, the design needs must be mentioned house with basement for parking. In big cities such as Hanoi, Ho Chi Minh City, etc., finding a car parking space is not an easy task, especially in parking areas with a roof.

Therefore, the cost of renting a car park becomes very high and becomes a burden for many families. For more convenience and cost savings, why not design? house with basement for parking.

    To meet that need Le Thy will bring you the fastest, safest and most economical basement construction solution. It is a construction method to dig open the basement using using Larsen poles and shoring kingpost bracing.

Construction and installation of shoring and excavation systems at the University of Fine Arts

 Construction and installation of shoring and excavation systems at the University of Fine Arts

    1. Design of basement construction methods

     Each of the solutions Le Thy brings to you is based on a scientifically calculated design before being put into construction. Based on the basement structure, the structure of your house combines geological data, groundwater level, the size and depth of the excavation, the load of surrounding vehicles, the load of neighboring structures, etc.

Le Thy's design engineers will calculate and give design drawings of Larsen piles (Larsen SPIII, SPIV, ...) shoring kingpost bracing system (H300, H350, H400, ...) and advise you on regulations construction process squeezing Larsen, install the safest and fastest bracing system.

Construction of basement with Larsen piles combined with Shoring kingpost system
Construction of basement with Larsen piles combined with Shoring kingpost system

    2. Construction larsen poles

    For construction works in big cities with narrow space and to limit noise and ground vibration, we will provide you with Larsen piling construction solutions. static pressing robot. Static pressing robot and Larsen pole are completely imported from Japan by Le Thy.

larsen beach
larsen beach
pressed larsen poles tofu channel
pressed larsen poles tofu channel

3. Construction, installation and dismantling of shoring kingpost bracing system, digging and transporting soil

Gia Dinh Shoes office building - HCM

 Gia Dinh Shoes office building - HCM

Construction steps, installation and dismantling of shoring kingpost bracing system, digging and transporting soil for Gia Dinh shoe project

  • Step 1: Dig the ground to a height of -2,500m (Compared to the natural ground level of -1,500m)
  • Step 2: Install class 1 (H350) anti-slip system at -1,850m (Compared to natural ground level -1,500m)
  • Step 3: Dig the soil to the elevation of -4,500m (Compared to the natural ground level of -1,500m).
  • Step 4: Install the layer 2 (H400) support system at an altitude of -3,500m (Compared to the natural ground level of -1,500m)
  • Step 5: Construction of digging the ground to the height of the bottom of the elevator foundation -7,050m 
  • Step 6: Construction of foundation & basement floor
  • Step 7: Remove the 2nd and 1st floor struts
  • Step 8: Construction of tunnel wall to cote -1,700m
  • Step 9: Construction of larsen piling
School building of Ho Chi Minh City University of Technology

School building University of Science and Technology America Art

nhamaydetnhuomriisesun

 Wastewater treatment tank Rise Sun textile dyeing factory - Tay Ninh

ubndcamau

 Headquarters of the People's Committee of Ca Mau province

khobaccamau

 Headquarters of State Treasury of Ca Mau province

The above is a method of basement construction using larsen pile walls combined with Shoring kingpost bracing system. With the available capacity and experience of a professional contractor, with a team of staff and workers who are trained and gradually trained through the construction of large projects across the country, Le Thy has full the ability to successfully complete the project with high quality with the fastest progress and absolute safety.