Ready-Built Factory Project No. 46 - Amata Industrial Park

  • Construction: Ready-Built Factory in Amata Industrial Park
  • Start: January 21, 2013
  • Category:
    • Providing piles, static test pressing, mass pressing
    • Factory installation and completion
  • Location: No. 46 – Amata Industrial Park, Bien Hoa, Dong Nai
  • Information about the bidding package:
    • We supply 2 test piles of reinforced concrete piles 300x300 – Concrete Grade 300.
    • Apply 2 test hearts. Pmax: 120 tons
    • Static test load and produce a document reporting the results of 2 test compression hearts
    • Providing 116 mass pile hearts, mass pressing piles.

Here are some construction photos from the "Prefabricated Factory Building No. 46 – Amata Industrial Park" project:

With a total construction progress of 28 days. Le Thy Construction Company Limited has completed the work on schedule, fast and safe construction, ensuring the quality of reinforced concrete piles as well as the pile pressing process in accordance with construction standards and regulations.