- Construction: Office Building – Ngo Han Joint Stock Company
- Category: Axial static compression test of 350×350 reinforced concrete pile.
- Location: 172/39/39E An Duong Vuong, Ward 16, District 8, City. HCM
- Investor: Ngo Han Joint Stock Company
- Construction unit: Le Thy Construction Company Limited
Here are some construction photos from the "Office Building - Ngo Han Joint Stock Company" project:


Testing information – Office Building Project
The center of the static test pile is the test pile located in the construction location. The piles used are load-bearing piles official structure after static testing. Reinforced concrete pile cross-section: 350 x350. Calculated load capacity of pile: Ptk= 73.34 tons. Maximum expected test load: Ptnmax= 150 tons. Expected maximum displacement: 35mm (10% pile cross-section).
Experimental methods
The experiment was conducted using the method of using static load applied axially to the reinforced concrete pile, so that under the effect of pressure, the pile sank deeper into the ground. The load applied to the pile head is done by hydraulic jacks with a reaction system that is a loading platform with a load of ≥ 120% Ptn, Ploadinmax = 1.2 Ptn. The load, displacement, and strain data obtained during the experiment serve as the basis for analyzing and evaluating the bearing capacity and load-displacement relationship of piles in the soil. Pile depth after testing 01 heart is 28.6 meters.
The experiment was conducted using the method of using static load applied axially to the reinforced concrete pile, so that under the effect of pressure, the pile sank deeper into the ground. The load applied to the pile head is done by hydraulic jacks with a reaction system that is a loading platform with a load of ≥ 120% Ptn, Ploadinmax = 1.2 Ptn. The load, displacement, and strain data obtained during the experiment serve as the basis for analyzing and evaluating the bearing capacity and load-displacement relationship of piles in the soil. Pile depth after testing 01 heart is 28.6 meters.
The project is in the process of static load testing and results are being reported.
Contact information:
- Address: No. 12, Street 27, Van Phuc Urban Area, Hiep Binh Phuoc Ward, Thu Duc City, HCMC
- Phone number: 0915.611.337 Mr. Phuong or 0915.411.337 Mr. Quan
- Email: [email protected] or [email protected]
- Website: Lethycorp.com
- Road Map: See